This project involved the execution of an emergency shoreline protection project at the Sand Pebbles Inn in Qualicum Beach, completed in December 2022. Following a severe storm that caused the collapse of an existing concrete wall, our team mobilized quickly to stabilize the area. The work included the installation of a rock revetment using large, angular blast rock to absorb wave energy and reinforce the coastline. This action successfully restored stability and created a durable barrier to safeguard the property from future storm impacts.
PROJECT KEY FEATURES
- Emergency Response and Site Stabilization
- Rock Revetment Installation
- Shoreline Protection and Restoration
PROJECT VALUE
$100,000